Develop a network diagram using AON method
ASSIGNMENT B
The Below table shows list of activities for a small project with the predecessors and duration for the project. There are seven working days in a week including Saturday and Sunday.
- Based on the information given develop a network diagram using AON method.
- Calculate the ES, EF, LS, LF for each activity on the diagram?
- What is the critical path of the project?
- List all the project activities in a table including the ES, LS, EF, LF, FF, TF as a number?
- List all the project activities in a table including their dates of ES, LS, EF, LF?
- Using the same table of Q4, Q5 to identify which activities are critical?
- Draw the Gantt chart for all the activities by Microsoft Excel using date and another Gantt chart using numbers?
- What is the total project duration? What is the project completion date?
ACTIVITY |
DURATION (days) |
PREDECESSOR |
START |
0 |
- |
Clear & Grub |
12 |
START |
Order & Delivery Reinforcement |
4 |
START |
Order & Delivery PC Slabs |
5 |
START |
Excavate Footings and Utilities |
7 |
Clean & Grub |
Delivery Frames, Channel etc |
9 |
Clean & Grub |
RC Footings |
9 |
Order & Delivery Reinforcement |
Form Footings |
12 |
Excavate Footings and Utilities (SS+2) |
Masonry & Bearing Walls |
9 |
Order & Delivery PC Slabs, RC Footings (FF +3) |
Erect Joists and Deck |
7 |
Masonry & Bearing Walls |
Foundation Block |
12 |
Delivery Frames, Channel etc, RC Footings (FS+4) |
Backfill |
9 |
Form Footings, Foundation Block |
FINISH |
0 |
Erect Joists and Deck, Backfill |