Develop a network diagram using AON method

ASSIGNMENT B

The Below table shows list of activities for a small project with the predecessors and duration for the project. There are seven working days in a week including Saturday and Sunday.

  1. Based on the information given develop a network diagram using AON method.
  2. Calculate the ES, EF, LS, LF for each activity on the diagram?
  3. What is the critical path of the project?
  4. List all the project activities in a table including the ES, LS, EF, LF, FF, TF as a number?
  5. List all the project activities in a table including their dates of ES, LS, EF, LF?
  6. Using the same table of Q4, Q5 to identify which activities are critical?
  7. Draw the Gantt chart for all the activities by Microsoft Excel using date and another Gantt chart using numbers?
  8. What is the total project duration? What is the project completion date?

ACTIVITY

DURATION

(days)

PREDECESSOR

START

0

-

Clear & Grub

12

START

Order & Delivery Reinforcement

4

START

Order & Delivery PC Slabs

5

START

Excavate Footings and Utilities

7

Clean & Grub

Delivery Frames, Channel etc

9

Clean & Grub

RC Footings

9

Order & Delivery Reinforcement

Form Footings

12

Excavate Footings and Utilities (SS+2)

Masonry & Bearing Walls

9

Order & Delivery PC Slabs, RC Footings (FF +3)

Erect Joists and Deck

7

Masonry & Bearing Walls

Foundation Block

12

Delivery Frames, Channel etc, RC Footings (FS+4)

Backfill

9

Form Footings, Foundation Block

FINISH

0

Erect Joists and Deck, Backfill